For several months the town of
Emmitsburg has been working on replacing a major sewer trunk
line. After some sewer spills, the Town Council agreed to
approve an emergency repair of approximately 3000 feet of a
twelve-inch diameter pipe that runs parallel to Flat Run. As
you can see, 14 months after the emergency repair was
approved, construction of this project has not yet begun.
The reason for such a long time to
begin construction is very simple but yet, it can be very
deceiving and misunderstanding to many. When the town
approves a project, it is done very much like most
individuals do when planning work or purchases within their
own households. Such as planning to purchase a new home,
doing some major home repairs or your considering the
purchase of a new car. No matter what it is, at some point
you must make the decision of which item you are going to do
next. Although you make the final decision, in most cases
that does not mean the money is available to pay off the
expense in full, immediately. Therefore, the next step is to
resolve how to pay for it. That is what the town did over a
year ago.
We approved the project and staff
was directed to find the funding. After contacting the
federal government and the state government to seek grant
and or low interest loan assistance, the federal government
did not offer any funding assistance; the Maryland
Department of Environment (MDE) offered a very low interest
loan for up to $600,000 with a 1.1 percent interest rate.
This funding was secured in the July 2003 Town Meeting.
After the money was secured, the
staff was then able to begin the process of having
engineering plans developed to define the scope of work. As
one of the conditions of the loan agreement, MDE must review
and approve the plans prior to the town advertising for
bidders. After MDE reviews the engineering plans and
provides the town with changes they request be incorporated
with the engineer plans, the plans are returned to our
engineering firm for corrections.
After all the appropriate reviews
and updates have been completed, the town may then move
forward on advertising the project. MDE also has strict
advertising requirements that must be followed. Bids are
normally accepted for a minimum period of 30 days. Once the
bidding period is over, all bids are opened and review by
the town's engineering firm. The engineering firm and the
town staff then make a contract recommendation to the Town
Council. Because MDE requires that the bidder with the
lowest responsible bid be awarded the contract, the Town
Council must make their approval contingent upon MDE's
approval.
After MDE confirms that they agree
with the Town Council's vote, the contract can then be
awarded and the contractor is given notice to proceed.
Normally on this size project the contractor will be given
30 days to mobilize his crews and equipment to begin work.
In our case, the town of Emmitsburg went through all the
above steps up to recommending a contractor for the sewer
trunk line.
The town received only one bid for
the project, which was nearly double the engineer's proposed
cost estimate. With only one bid at nearly double the
expected cost of $350,000 to $400,000, the town rejected the
lone bid of just over $700,000 and decided to modify the
scope of work and re-bid the project to provide an
opportunity for other bidders to bid on the project.
Currently the town is having those improvements made to the
engineering plans. We are expecting to be re-bidding the
project within the next 30 days.
As you can see, there are many steps
required to begin a project, securing a funding source,
creating engineer plans, MDE approval, bidding process, bid
approval, award contract, contractor mobilizing crews and
equipment, etc. All of these and many other requirements
take a minimum of 30 days each, many such as funding
approval, creating engineering plans, MDE review and
approval of plans normally take 60 to 120 days each (and
sometimes more). Since most requirements must be completed
before the next one can be approved, many items cannot be
done simultaneously.
The town also has other projects in
the works. Mountain View Road water line construction is set
to begin mid May 2004 and engineering plans are currently
being updated to replace the water line in South Seton
Avenue. Also in the upcoming budget, I plan to have at least
one other sewer line project identified with funding coming
from the new Sewer and Water Enterprise Fund. By
establishing a dedicated budget separate from the town's
general fund, the town's Sewer and Water Enterprise was
finalized last year. With the Sewer and Water Enterprise
Fund in place, the town can seek funding for some projects
in-house without the need to look for state and or federal
loans.
If you have any questions, please
feel free to call the town office, or e-mail me at
mayorhoover@emmitsburgmd.gov
Respectfully,
Jim Hoover
Read Past Issues of 'From Mayor Jim's Desk'