Town Manager's
Report May
2006
Prepared by
David Haller
Streets:
- The curb and sidewalk
has been repaired and the curb-cut removed on West
Main at School Lane
- Staff has installed a
parking space and meter at the old entrance to
School Lane on West Main Street
- Staff has repaired and
relocated a number of street signs
- Staff installed the
American Flags on Main Street
Water:
- Staff has flushed the
raw line from Rainbow Lake to the water treatment
plant
- The roughing filters are
being backwashed everyday and the DE filters every 7th
day
- The pilot plant
clarifier has been delivered and testing operations
will begin very soon
- Staff has completed the
state mandated "Consumer Confidence
Report"
- The lab area
enclosure has been completed at the water treatment
plant as recommended by MDE
- Water production and
consumption. We produced and purchased an
average of 381,094 gpd. We consumed an average
of 371,242 gpd.
- The difference is
"Backwash Water" ...(2.6%). We purchased
397,250 gals. of water from MSM this month.
- 59.1% of this water
came from wells
- 3.3% of this
water came from Mt. St. Mary's
- 37.6% of this water
came from Rainbow Lake
Wastewater:
- We had one raw sewerage spill in the Month of May
@ MH S-15 on May 11th 1,222 gal. We received
1.9" of rain that day
- We received about 3.3
inches of precipitation this month (the average is 4.5
inches)
- We are 5.o"
short on precipitation over the last six months
- 74% or 3.5"
of that shortage came in March when we only
received 0.5" of precipitation
- Wastewater Treatment:
- We treated an average
of 406,000 gpd (consumed 371,242 gpd) which means
that 8.6% of the wastewater treated this month was
"wild water"
- We exceeded the
plant's design capacity two days in the month of May
5/11 .... 1,056,000 gpd
5/15 ... 1,116,000 gpd
Trash:
- Trash pickup days will
remain Monday & Thursday for the month of June
Parks:
- Staff has painted the
floor in the pool building
- Staff installed the
posts and cable at the farmer's market
- Staff has completed the
installation of the bike rack at the Community
Center
- Staff and a contractor
have completed the repairs to the electrical supply
system and the bathrooms in Memorial Park
Meetings
Attended:
- 05/10 Frederick County
Building Managers Meeting
- 05/11 Sesquehanna Ban-
related to purchase of 140 S. Seton Avenue
- 05/12 With Fox &
Assoc. related to South Seton Avenue project
- 05/12 Emmitsburg Glass
Co. & County Plumbing Inspector related to their
new building
- 05/19 Developer of
Brookfield related to Section III Build-out
- 05-23
Pre-Construction meeting - Community Park bathrooms
- 05/26 Progress
meeting - Creamery Road sewer project