Streets:
-
Staff
maintained flower hanging pots on the square
-
Staff has
repaired a number of street lights
-
Staff worked
with Frederick County Paving to resurface the streets
in Emmit Gardens
-
Staff
worked with S&W Construction to repair the
sidewalk at 130 West Main St.
-
Staff
cleaned East & West Main Streets
Water:
-
Rainbow Lake
is now about 19" below the spillway (down from
8" last month) and all wells are starting to
slowly drop
-
The roughing
filters are now being backwashed twice per day
and the DE filters are being done once per week
-
A new
transducer has been installed in Tank No. 1. We
have been running on Tank #2 with tank #1 controlling
flows the plant has been operating much smoother
Water
production and consumption. We produced and
purchased an average of 363,114 gpd. We consumed
an average of 301,252 gpd
-
The
difference is "Backwash Water" ...(17.0%). We purchased
735,300 gals.
of water from MSM this month.
-
45.2% of this
water came from wells
-
6.5% of this water
came from Mt. St. Mary's
-
48.3% of this
water came from Rainbow Lake
Wastewater:
-
Staff is
continuing to operate the overland flow treatment
system
-
We received
about 2.0 inches of precipitation this month (the
average is 3.6 inches)
-
Wastewater
Treatment:
-
We treated
an average of 257,000 gpd (consumed 301,252 gpd)
which means that 0.0% of the wastewater treated this
month was "wild water".
-
We
experienced no spill of untreated sewerage
during the month of August
-
We did not exceed the plant's design capacity
during the month of August
Trash:
Parks:
-
Staff made all
standard checks and emptied trash cans
-
Staff installed a new grill at Silo Hill
Park
-
Staff
installed ballfield mix on Babe Ruth Field
-
Staff dug
out a dead tree in Memorial Park and replaced it with
a new one ...(one of Ms. Boyles' trees)
-
Staff
installed new information boards in Community and
Memorial Parks
-
Staff
performed standard mowing and trimming
Meetings
Attended:
-
08/05 EEIP
contract meeting with town attorney
-
08/07 LEPC -
Emergency Planning meeting
-
08/08 Meeting
with consultants and engineers related to proposed
Emmit Gardens water treatment plant
-
08/12 Meeting
with St. Joseph's Church and their contractor related
to an on-site water main relocation
-
08/13 Meeting
with pool contractor
-
08/13
Meeting with Emmitsburg Early Learning Center
-
08/19
Meeting with Planning staff
-
08/19 LEPC
- Drill Planning Course
-
08/21 LEPC
- Emergency Planning meeting
-
08/22
Staff meeting related to chemical storage policy
-
08/27
Meeting with property owner related to POS land
purchase
list