Streets:
-
Staff
maintained flower hanging pots on the square
-
Staff has
repaired a number of street lights
-
Mr. Striper
painted centerline & parking on Silo Hill Road
-
Staff
installed bollards along South School Lane
-
Staff
replaced "No Parking" signs on Frailey Road
Water:
-
Rainbow Lake
is now about 8" below the spillway, but our five
wells appear to be holding up well
-
The roughing
filters are now being backwashed twice per day
and the DE filters are being done once per week
-
Staff has
recently drained, cleaned and refilled water storage
tank No.1 (500,000 gals)
Water
production and consumption. We produced and
purchased an average of 348,036 gpd. We consumed
an average of 298,454 gpd
-
The
difference is "Backwash Water" ...(14.2%). We purchased
739,000 gals.
of water from MSM this month.
-
46.0% of this
water came from wells
-
6.8% of this water
came from Mt. St. Mary's
-
47.2% of this
water came from Rainbow Lake
Wastewater:
-
Staff is
continuing to operate the overland flow treatment
system
-
We received
about 2.2 inches of precipitation this month (the
average is 3.6 inches)
-
Wastewater
Treatment:
-
We treated
an average of 269,000 gpd (consumed 298,454 gpd)
which means that 0.0% of the wastewater treated this
month was "wild water".
-
We
experienced no spill of untreated sewerage
during the month of July
-
We did not exceed the plant's design capacity
during the month of July
Trash:
Parks:
-
Staff made all
standard checks and emptied trash cans
-
Staff repaired ball field fences
-
Staff
repaired ladders at the swimming pool
-
Staff cut
down a dead tree in Memorial Park
-
Staff
repaired chlorine pump at swimming pool
-
Staff
performed standard mowing and trimming
-
Staff
installed new low barrier fence at swimming pool
parking lot
Meetings
Attended:
-
07/01 Met
engineers related to subdivision of existing property
known as Seton Square
-
07/02 Met with
HR consultant
-
07/02 Met with
Amy Naill and pool contractor
-
07/07 Met with
P&Z staff related to permitting process
-
07/09 Met with
trash pick-up contractor
-
07/09
Shelter-In-Place meeting
-
07/10 LEPC
- Emergency Planning meeting
-
07/14 Met
with Gettysburg Times reporter related to town meeting
items
-
07/15
Lincoln Avenue water & sewer rehab project meeting
-
07/16 Met
with Amy Naill and pool contractor
-
07/17 BOCC
waste to energy meeting
-
07/17 BOCC
& Municipal meeting
-
07/24 LEPC
- Emergency Planning meeting
list